Category A
For projects classified as category A, GIEK will publish the environmental and social impact analysis here:
Name |
Country |
Type |
Report |
| Tanga | Tanzania | Heavy fuel thermal power. |
EIA For70MW Majani Mapana TANGA |
| Kinyezeri | Tanzania | Thermal Power Plant |
ESIA Kinyerezi 20_02_2012 FINAL_COMPRESSED 1
Appendices 1 to 15 |
| Sawalkot | India | Energy, hydropower |
You will find the 1st part of the environmental report from the project in two separate files:
2nd part, which will deal with social problems, is being prepared. |
| Qatalum | Qatar | Aluminum plant |
EIA-report and EIA-summary, look here: www.qatalum.com Published 21.08.07 |
|
Guaigüí |
Dominican Republic |
Water and energy |
EIA-rapport Guaigüí del I |
| Mputa | Uganda |
Heavy fuel power plant and transmission lines. The project concerns the construction of a 57 MW power plant in addition to 132kV high-voltage lines, in order for the power to be transmitted to the main power grid. The line will be approx. 200 km long. The power plant will consist of 7 engines operated on heavy fuel, crude oil and diesel. In this plant, heavy fuel will be used to generate electricity. 7 MW will be used to operate the plant itself and approx. 50 MW will be transmitted to the high-voltage lines. |
EIA report Mputa Annexes Mputa Publisert 17.06.08 EIA transmisjonslinjer Mputa Publisert 23.09.08 |
| Kabaale | Uganda | Thermal Power Plant |
EIA report Kabaale Published 17.01.11 |
|
Reliance Industries Ltd. |
India |
Energy. Deliveries to the construction of the oil and gas field KG-D6 on the Indian shelf. |
Contact GIEK for the EIA report. Published 04.07.08 |
|
Las Placetas |
|
|
EIA-rapport Las Placetas: Chapter 1 Chapter 2 Chapter 3 Chapter 4 Chapter 5 Chapter 6 Chapter 7 Chapter 8 Tabeller chapter 8 (1) Tabeller chapter 8 (2) Chapter 9 Published 20.11.08
Socioeconomic survey Published 25.02.11 |
| Sakhalin | Russia | Delivery of two ferrries intended for transport of personnel. |
EIA-report: www.sakhalinenergy.com
Marine Operating Procedures and Guidelines |
| Dubai LNG Regasification Project | Dubai | Fleet for stationary placement |
ESHIA-rapport: Chapter 1 Chapter 2 Chapter 3 Chapter 4 Chapter 5 Chapter 6 Chapter 7 Chapter 8 Chapter 9 Chapter 10 Chapter 11 Chapter 12 Chapter 13 Binder Contents Title Non-Technical Summary Glossary Appendix: A B C D E F G H Binder Title Contents Published 13.10.09 |
|
Ubungo
|
Tanzania |
Gas power
|
Published 15.12.10 |
| Bajo Frio | Panama |
Hydropower
|
Published 15.12.10
|
| Helguvik | Iceland | Silicon raw material for photovoltaic cell production |
Published 13.01.11 |
Category B
According to the OECD rules, information regarding B projects are to be published on an annual basis, after the policy has been issued:
Name |
Country |
Type |
Report |
| Namanve | Uganda | Energy, thermal power. |
Final report Namanve Please contact GIEK for appendixes. Policy issued in 2007. |
Stakeholder Complaint Mechanism:
GIEK is required under OECD regulations to publish environmental and social impact information at least 30 days prior to granting a guarantee. Stakeholders wanting to raise a grievance or provide additional information with regard to negative environmental and social impacts are welcome to do so. For additional information, or to submit inquiries related to the complaint mechanism, please contact:
Øyvind Ajer
Ass. Managing Director, Underwriting Department
Phone.: 951 22 598
E-mail: oyvind.ajer@giek.no
Kamil Zabielski, Senior Advisor, Social and Human Rights Analysis
Phone: 41044914 E-mail: kamil.zabielski@giek.no
Bjørn Egeland, Senior Advisor, Environmental analysis
Phone: 95925679 E-mail: bjorn.egeland@giek.no